27.01.2018

Saerbeck, 26th January 2018

THE DAY AFTER – SAERTEX® AND SAERTEX multiCom® RESUME OPERATIONS

Almost 24 hours to the minute after the fire alarm was triggered, operations at SAERTEX GmbH & Co. KG have resumed at 100 per cent. Employees in the administration and production have been back on the job since 06:00 a.m. The same applies to the administration of SAERTEX multiCom GmbH. Clean-up operations have commenced at the SAERTEX multiCom production plant. Management is relieved that no one was injured, and would like to thank the more than 300 responders of the fire department, the THW (Technical Relief Service) and the German Red Cross – as well as all SAERTEX employees.


"Yesterday was a huge shock for us all. We are very glad that none of the employees, none of the emergency responders and, above all, none of the residents were injured by the fire in Saerbeck", states a relieved Simon Lammers, Vice Chairman of the SAERTEX Group. "The event has shown us how well our employees can pull together under extreme circumstances. We will be doing our utmost to resume production at SAERTEX multiCom as soon as possible. I would like to express special thanks to the more than 300 emergency responders who, with their professional work yesterday, gave everything to protect our employees’ life and limb and to minimise the material damage", adds Frank Mersmann, Managing Director of SAERTEX multiCom GmbH.

In the early morning hours of January 25th, the fire alarm was triggered in the 5,000 square metre production and storage facility of SAERTEX multiCom in Saerbeck. During the course of the day, more than 300 emergency responders were deployed on the plant premises. A significantly smaller contingent of approximately 30 responders is now taking care of the last smouldering nests and securing the scene of the fire. The fire department expects to be done in the course of this afternoon.

At the same time, clean-up is commencing in the production and warehouse area of SAERTEX multiCom. Since the early hours of this morning, operations have resumed in the administrative area of SAERTEX multiCom GmbH as well as in the production and administrative areas of SAERTEX GmbH & Co. KG.

 

Back to the overview

Saerbeck, June 2019

APP FOR THE PIPE SYMPOSIUM ONLINE!

Do you already know our new app for the 8th Saerbeck Pipe Symposium? Here you will find all information about the event in September in Münsterland. Whether programme, exhibitor, side programme or registration: Everything online and always up to date!

Read more...


Saerbeck, June 2019

LOOKING FOR SOMETHING NEW? THAT MEETS WELL!
CHCESZ SPRÓBOWAĆ? DOBRZE SIĘ SKŁADA!

For our headquarter in Saerbeck (Homeoffice in Poland possible) we are looking for a sales representative in Poland (m/f/d). Are you interested? We are looking forward to your application!

Check here.

Read more...


Saerbeck, April 2019

WELCOME TO SAERBECK

Don’t miss out on September 26 or 27, 2019, when we open the doors to the Saerbeck Pipe Symposium at our head office here in the Münster region! It will be the 8th symposium in the more than 20-year company history of SAERTEX multiCom®.

Read more...


Saerbeck, January 2019

JUST ONE YEAR AFTER THE MAJOR FIRE...

... we start the new year as if (almost) nothing had happened. 

Read more...


Saerbeck, December 2018

As for the future, your task is not to foresee it, but to enable it. (Antoine de Saint-Exupéry)

The year is coming to a close, and so we cast our eyes toward the promise of 2019. The big fi re at the end of January 2018 showed us that, with a partner like you at our side and a motivated team behind us, we can overcome even the greatest of challenges.

Read more...


Saerbeck, 10th October 2018

Inventory & company holidays in December (Plant Saerbeck)

Due to our annual inventory we would like you to take following dates into consideration during your planning. Our office team will be available to assist as usual.

Read more...


Saerbeck, 01st October 2018

8TH SAERBECK PIPE SYMPOSIUM: 26. & 27.09.2019

On these days we will open the doors to the 8th Saerbeck Pipe Symposium in Münsterland.

Of course you will again find exciting lectures, interesting exhibitors in the indoor and outdoor area, live demonstrations and a great evening programme.

Read more...


Saerbeck, 06th June 2018

"SCHOOL GRADE" 1.5 FOR THE SHAFT-LINER OF SAERTEX multiCom

Our long-standing customer Swietelsky-Faber scored "very good (1.5)" with its SF shaft liner in a retest of the ICT product test "shaft rehabilitation". 

At our booth at IFAT in Munich last week, IKT-Managing Director Roland W. Waniek presented the IKT product test seal to Jörg Brunecker, Managing Director of Swietelsky-Faber.

Read more...

Saerbeck, 19th October 2017

New production and warehouse facility for SAERTEX multiCom

The construction work began early October on a new warehouse and production facility for SAERTEX multiCom at the site in Saerbeck. The project involves the installation of additional new production systems to expand the capacity for GRP-liners at the facility, which covers a surface area of  4,500 m2. The field of house connection liners (HASE) is being expanded with new areas, especially for the packaging, the impregnation, and the storage of the new light-cured liner.

Read more...