After the pipe section has been closed off, cleaned and TV-inspected, rehabilitation works can begin and the flow of traffic can continue.
|
|
The sliding film is drawn in, at the same time the working packers are installed at the ends of the liner.
|
|
The liner is drawn into the existing pipe and then inflated using compressed air.
|
|
Curing of the installed liner under UV light or steam can start.
|
|
The entire computer-controlled curing process is supervised and the rehabilitated construction area can be put into operation again on the same day.
|